Commercial· Education
School Electrical Containment Upgrade
Power • Data • Fire Alarm
Following the removal of a suspended grid ceiling at a school, existing cabling was left exposed and unsupported within the corridor void. Scammell Electrical Solutions was brought in to provide a permanent containment solution that would safely support and organise the different cable systems.
- Electrical containment
- Cable management
- Commercial project works

- Education
- Commercial environment
- 3 dedicated routes
- Power • Data • Fire Alarm
- New containment
- Following ceiling removal
The challenge
With the original ceiling grid removed, cables previously supported within the void were left hanging and, in some areas, dropping down towards floor level. A new containment route was needed to restore support, improve organisation and maintain separation between different electrical systems.
Our solution
We installed a new segregated containment system throughout the affected areas. The system was arranged into three dedicated routes for power cabling, data cabling and fire-alarm cabling. The containment was fixed securely along the corridor routes and adapted around doorways, corners and existing building features.
On site
Select a photograph to view it in full.
Segregated routes
The installation was arranged into three dedicated containment routes, keeping the power, data and fire-alarm systems separated along the corridor.
The result
The completed containment installation provided a structured, supported and clearly separated route for the existing services following removal of the suspended ceiling. The result was a cleaner, more maintainable installation with the different cable systems organised into dedicated containment routes.

Related services
Need electrical containment or infrastructure upgrades?
Speak to Scammell Electrical Solutions about containment, cable management and electrical project works for commercial and education environments.
Other commercial projects

Emergency Warehouse Lighting Restoration
Following a warehouse-wide lighting failure, we investigated the fault, arranged high-level access equipment on site in under four hours and carried out remedial work to restore the lighting.

Reactive Entrance Heater Replacement – London
A failed over-door entrance heater was removed and replaced at a London building entrance, with the works carried out outside normal opening hours to avoid disrupting the premises.